Great news from the Alu-Frost factory in Poland. Last Friday we successfully commissioned and tested the energystorage installed as part of the #MESH4U project!
For the duration of the commissioning tests, the power supply at the factory was turned off, and the storage successfully transmitted energy during this time, ensuring uninterrupted operation of the plant.

This is not the end of our work, as we will be conducting further tests of various scenarios over the next few weeks to optimize the energystorage operation to the #maximum.